Which times are used for Basic Date Scheduling of manufacturing planned orders in MRP? Select the correct options.

Prepare for the SAP Production Planning and Manufacturing Exam. Study with expertly crafted flashcards and multiple-choice questions, each question complete with hints and detailed explanations. Boost your confidence and get ready for your certification!

In the context of Basic Date Scheduling for manufacturing planned orders in Material Requirements Planning (MRP), it's essential to understand the role of various time factors and how they contribute to scheduling.

Setup time is the correct choice because it refers to the amount of time required to prepare a production process before actual manufacturing begins. This includes aligning machinery, gathering materials, and configuring tools necessary for production. Properly accounting for setup time is crucial, as it impacts the overall lead time for manufacturing processes. If setup time is not considered, planned orders may be scheduled inaccurately, leading to delays and inefficiencies in the production schedule.

The other options, while relevant to different aspects of production planning, do not play a direct role in the Basic Date Scheduling of manufacturing planned orders. Understanding the specific contributions of setup time helps reinforce the importance of each phase in the manufacturing execution timeline.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy