Which data object is updated with the scheduling results of a routing?

Prepare for the SAP Production Planning and Manufacturing Exam. Study with expertly crafted flashcards and multiple-choice questions, each question complete with hints and detailed explanations. Boost your confidence and get ready for your certification!

The material master is the data object that is updated with the scheduling results of a routing because it contains all the essential information related to the material, including production planning and scheduling details. When routing information is processed during production scheduling, the results, such as lead times and production quantities, are reflected in the material master.

This integration ensures that planners have up-to-date information about material availability, production scheduling, and associated resources. It plays a crucial role in material requirements planning (MRP) and helps in tracking production efficiency and timelines effectively.

In contrast, the production scheduling profile typically defines how production orders are created and managed but does not store scheduling results. The production version combines routing and bill of materials for a specific material but is not the primary object for storing results from routing scheduling. The MRP profile focuses on the planning strategies and settings used during the MRP run rather than direct scheduling output, making the material master the correct answer in this context.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy