When modeling goods receipt processing time in Detailed Scheduling, what options are available? (Select two)

Prepare for the SAP Production Planning and Manufacturing Exam. Study with expertly crafted flashcards and multiple-choice questions, each question complete with hints and detailed explanations. Boost your confidence and get ready for your certification!

When considering the options available for modeling goods receipt processing time in Detailed Scheduling, it is essential to understand the roles and characteristics of the proposed resources.

Modeling a transportation resource in the location master is a valid approach because it allows for the inclusion of transportation times as part of the goods receipt process. This resource captures the time involved in moving products from one location to another, contributing to an accurate depiction of the overall processing time from the moment products arrive at a location until they are registered as received. Ensuring that transportation is factored into the scheduling process is crucial for achieving realistic timelines and optimizing delivery and inventory management.

The correct option also includes modeling a handling resource in the location master and goods receipt time in the material master. This method allows businesses to categorize and manage handling times for goods once they arrive at their destination. By associating handling resources with specific locations and defining the goods receipt time in the material master, the scheduling system can provide a more comprehensive view of how long it takes for goods to be processed upon arrival. This ensures that all phases of the goods receipt, including handling and inspection, are accounted for in the scheduling process, allowing for better planning and allocation of resources.

Through these approaches, businesses can achieve greater accuracy in their detailed scheduling